Institutional

Artist rendition by Salter Pilon Arch.

In Progress - Oro-Medonte Public School & Community Centre

Owner: Simcoe County District School Board & Township of Oro-Medonte
Consultant: Salter Pilon Architecture Inc.
Date Completed: In progress
Project Value: $29 Million
Scope of Work: New School and Community Centre

Artist Rendition by Hossack Assocaites

UNDER CONSTRUCTION

In Progress - Kleinburg Public School

Owner: York Region District School Board
Consultant: Hossack & Associates Architects
Date Completed: In progress
Project Value: $22 Million
Scope of Work: New School Construction.

Artist Rendition by Hossack & Associates

In Progress - Aurora #2 Public School

Owner: York Region District School Board
Consultant: Hossack & Associates Architects
Date Completed: In progress
Project Value: $24 Million
Scope of Work: New School Construction.

Central York Fire Sevices

Central York Fire Sevices

Artist Rendition

Central York Fire Services Headquarters Station 4-5

Owner: Town of Aurora
Consultant: Thomas Brown Architects Inc.
Date Completed: Completed August 2022
Project Value: $13 Million
Scope of Work: New construction of a 2-Storey, 2,204m2 Central York Fire Services headquarters facility which will incorporate Offices, a Training Centre (indoor and outdoor), an Apparatus Bay and living quarters for the fire services personnel.

Construction will consist of reinforced poured concrete foundations with load-bearing structural steel framing supporting the composite floor deck and hollow-core precast floor structures for the Mezzanine and Second Floor respectively.  Ground Floor will be supported by a poured concrete slab-on-grade.  The roof structure will be comprised of steel roof deck atop structural steel trusses and joists.

Bayview Glen Private School - Addition and Renovation

Owner: Bayview Glen / Moatfield Foundation
Consultant: ward99 Architects
Project Value: $20 Million
Scope of Work:  General construction of a two storey addition and renovation to an existing three storey private school. Work includes addition to existing building, new pool, demolition of temporary gymnasium structure,  associated sitework, extensive shoring and caisson work, and below grade items within the property line. The work includes but not limited to; new sod, trees, and landscaping between the front property line and edge of the street pavement; new concrete sidewalk extension from the property line to the municipal sidewalk, and work outside the property for utility lines, connections to utility mains, concrete sidewalk, curbs and asphalt pavement work between the property lines and the street curb at two new roadway entrances.

Rendering by MG Architects 

In Progress - Pte. Buckam Singh Public School

Owner: Peel District School Board
Consultant: MG Architects Inc.
Date Completed: March 2021
Project Value: $16 Million
Scope of Work:  New construction of a two storey elementary school. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes including but not limited to lockers, stage performance lighting, elevator,  and all typical finishes. All site work includes site servicing, paving, curbs, sidewalks, sodding, fencing, and landscaping.

Rendering by MC Architects

Viola Desmond Elementary School (Formerly Block 12 ES)

Owner: York Region District School Board
Consultant: MC Architects Inc.
Date Completed: October 2019
Project Value: $14.5 Million
Scope of Work:  New construction of a two storey elementary school. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes including but not limited to lockers, stage performance lighting, elevator,  and all typical finishes. All site work includes site servicing, paving, curbs, sidewalks, sodding, fencing, and landscaping.

3190 Mavis Paramedic Station - Fuel Island

Peel Regional Paramedic Services - Mavis Satellite Station

Owner: The Regional Municipality of Peel
Consultant: Reinders + Rieders
Date Completed: August 2018
Project Value: $19 Million
Scope of Work:  New construction of a 3150mfacility to be occupied by Accessible Transportation (TransHelp) and Peel Regional Paramedic Services (PRPS) Satellite Station.

This project features the following; Vehicle Repair Garage, Indoor Vehicle Storage and Staging Area, Automatic Vehicle Wash Bay, New Fuel Island, Green Roof, Water Harvesting System, Offices, Meeting Rooms and Lunch Rooms.

This project involved extensive contaminated soil removal and remediation.

 

Victoria Square Public School

Owner: York Region District School Board
Consultant: Synder Architects
Date Completed: August 2018
Project Value: $12 Million
Scope of Work:  New construction of a two storey elementary school. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes including sun shades, scoreboard, blinds, and all typical finishes. All site work includes site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and shade structures.

Dolson Public School

Dolson Public School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architects Inc.
Date Completed: August 2018
Project Value: $14 Million
Scope of Work:  New construction of a two storey elementary school. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes including scoreboard, blinds, and all typical finishes. All site work including site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and irrigation system.

Rendering by Moffet & Duncan Architects

Viola Desmond Public School

Owner: Durham-District School Board
Consultant: Moffet & Duncan Architects Inc.
Date Completed: August 2018
Project Value: $15 Million
Scope of Work:  New construction of a two storey elementary school. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes including scoreboard, blinds, and all typical finishes. All site work including site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and in-ground solid waste bins.

Jean Augustine Secondary School

Jean Augustine Secondary School

Owner: Peel District School Board
Consultant: CS&P Architects Inc.
Date Completed: August 2016
Project Value: $36 Million
Scope of Work:  New construction of a three storey, 19,500 m2 Secondary School. Building consists of structural steel, steel deck & reinforced poured concrete and non load bearing masonry partitions. All interior finishes including food preparation equipment. All site work including site servicing, paving, curbs, sidewalks, sodding, fencing, and landscaping.

St. Alphonsa Catholic Elementary School

Owner: Dufferin-Peel District School Board
Consultant: Allen & Sherriff Architects Inc.
Date Completed: September 2016
Project Value: $10 Million
Scope of Work:  Construction of a New School/Library. Building consists of load bearing masonry walls, prestressed concrete slabs, structural steel, and all interior finishes. All site work including site servicing, paving, curbs, sidewalks, sodding, fencing, interior & exterior landscaping and irrigation.

Tribune Public School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architects Inc.
Date Completed: November 2016
Project Value: $13 Million
Scope of Work:  New construction of a two storey Public School. Building consists of structural steel, steel deck & reinforced poured concrete and load bearing masonry walls. All site work including site servicing, paving, curbs, sidewalks, sodding, fencing, and landscaping.

Alloa Public School

Alloa Public School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architects Inc.
Date Completed: August 2015.
Project Value: $15 Million
Scope of Work:  Construction of a new School. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes. All site work includes new septic system, underground water and fire tanks, site servicing, paving, curbs, sidewalks, sodding, fencing, and landscaping. Work was completed on time with very tight time restraints.

Robert Munsch

Robert Munsch Public School

Owner: York Region District School Board
Consultant: IBI Group Architects
Date Completed: July 2014
Project Value: $8 Million
Scope of Work: Construction of a new school. Building consists of load bearing masonry walls, pre-stressed concrete slab, structural steel, and all interior finishes. All site work includes site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and irrigation system.

See below for a time lapse of the project

Lorenville P.S. Image 1

Lorenville Public School

Owner: Peel District School Board
Consultant: Hossack & Associates
Date Completed: August 2013
Project Value: $ 10,240,000.00
Scope of Work: Construction of new School and Library and all interior finishes, all site work including site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and irrigation system.

Sir Isaac Brock Public School

Sir Isaac Brock Public School

Owner: Peel District School Board
Consultant: MG Architects Inc
Date Completed: August 2013
Project Value: $ 10,519,000.00
Scope of Work: Construction of new school and Library and all interior finishes. All site work including site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and irrigation system.

“Sir Isaac Brock will be a great namesake for the school to use to build historic connections and understanding.” Brampton Guardian March 9, 2013

Ray Lawson

Ray Lawson Public School

Owner: Peel District Board
Consultant: Moffet & Duncan Architects
Date Completed: August 2012
Project Value: $10,250,000.00
Scope of Work: Construction of a New School and Library and all interior finishes. All site work including parking lot, curbs, sidewalks, fencing, site services and landscaping including irrigation system.

Beryl Ford Public School

Beryl Ford Public School

Owner: Peel District School Board
Consultant: MG Architects Inc
Date Completed: August 2012
Project Value: $ 10,135,000.00
Scope of Work: Construction of a new School and Library and all interior finishes. All site work including parking lot, curbs, sidewalks, fencing, site services and landscaping.

Southfields

Southfields Village Public School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architects
Date Completed: June 2012
Project Value: $ 11,300,000.00
Scope of Work: Construction of a new School and Library and all interior finishes. All site work including parking lot, curbs, sidewalks, sodding, fencing, site services and landscaping including irrigation system.

Southfields Village Public School is a kindergarten to grade 8 school. Southfields Village is the first school in the Peel board that is powered by geo-thermal energy which heats and cools the entire building while maintaining a comfortable temperature for learning all year round

 

Picture3

Mount Pleasant P.S. Village Community Center & Library

Owner: Peel District School Board
Consultant: Makrimichalos Cugini Architects
Date Completed: August 2011
Project Value: $15,300,000.00
Scope of Work: New 2 storey school for the PDSB and a library/cultural amenity space for The City of Brampton with exterior ice-rink, wading pool. Building consists of load bearing masonry walls, pre-stressed concrete slabs, structural steel, all interior finishes and all site work including site servicing, paving, curbs, sidewalks, sodding, fencing, landscaping and irrigation system.

James_Grieve

James Grieve Public School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architects
Date Completed: August 2011
Project Value: $ 10,500,000.00
Scope of Work: Construction of a new School and Library and all interior finishes, all site work including parking lot, curbs, sidewalks, fencing, site services, landscaping including irrigation system and 1 kilometer of new road work.

Pic_Placeholder

North Park Secondary School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architect Inc
Date Completed: July 2010
Project Value: $ 4, 700,000.00
Scope of Work: Two-storey addition and renovation to existing school and includes all site work including parking lot, curbs, sidewalks, fencing, site services and landscaping. Work was completed in an occupied environment.

Pic_Placeholder

Palgrave Public School

Owner: Peel District School Board
Consultant: Moffet & Duncan Architects
Date Completed: June 2009
Project Value: $ 11,025,000.00
Scope of Work: Construction of new School and Library and all interior finishes. 1.3 million Septic system, and demolition of an existing school and all site work including parking lot, curbs, sidewalks, sodding, fencing, site services and landscaping.

Burnt Elm

Burnt Elm Public School

Owner: Peel District School Board
Consultant: Makrimichalos Cugini Architects
Date Completed: August 2008
Project Value: $ 3,670,000.00
Scope of Work: Two-storey addition and renovation to existing school and all site work including parking lot, curbs, sidewalks, fencing, site services and landscaping. Work completed in an occupied environment.